Budget Control in SAP
Budget Control
•For
controlling purpose, Budget Availability Control for AFE has been activated in
SAP
•The
Availability Control will calculate Budget Availability (remaining value
percentage) based on budget set on lowest WBS level (for posting) compared to
the spending (commitment + actual)
–Budget
commitment : Budget reservation for consumption
–Budget
actual : Budget consuming posting data
•Budget Availability Control :
–Warning
on 70% spending
–Error
on 100% spending
•If
any budget revision made to the respective AFE / Cost Center, budget control
validations will refer to the revised budget (not the original)
Budget
Monitoring
a.
Original Budget = Amount budget uploaded
(tcode: CJ30)
b.
Supplement = Additional budget amount
for revision (tcode : CJ37)
c.
Return = Less budget amount for revision
(tcode : CJ38)
d.
Total Budget = Total budget release
(tcode : CJ32)
e.
Actual = Total amount from actual
posting, exclude settlement
f.
Commitment = Amount from PR, PO, and
Reservation
g.
Total Cost = Actual + Commitment
h.
Usage (%) = Total Cost / Total Budget
i.
Remaining (%) = 100% - (Total Cost/Total
Budget)%
Budget Revision
•Budget
revision proposal should be addressed to VP Finance & Performance along
with the proper justifications.
•Once
the budget revision proposal is approved by VP Finance & Performance, it
should be informed to Accounting for supplement & return process in SAP
•Budget
Commitment in SAP is on :
–Purchase
Requisition Final Approval
–Purchase
Order Final Approval (including VAT)
•Budget
Actualization in SAP is on :
–Service
: Service Entry Approval
–Goods
: Goods Issue posting