Budget Control in SAP

Budget Control

For controlling purpose, Budget Availability Control for AFE has been activated in SAP
The Availability Control will calculate Budget Availability (remaining value percentage) based on budget set on lowest WBS level (for posting) compared to the spending (commitment + actual)
Budget commitment : Budget reservation for consumption
Budget actual : Budget consuming posting data
Budget Availability Control :
Warning on 70% spending
Error on 100% spending
If any budget revision made to the respective AFE / Cost Center, budget control validations will refer to the revised budget (not the original)



Budget Monitoring
a. Original Budget   = Amount budget uploaded (tcode: CJ30)
b. Supplement   = Additional budget amount for revision (tcode : CJ37)
c. Return   = Less budget amount for revision (tcode : CJ38)
d. Total Budget   = Total budget release (tcode : CJ32)
e. Actual  = Total amount from actual posting, exclude settlement
f. Commitment   = Amount from PR, PO, and Reservation
g. Total Cost   = Actual + Commitment
h. Usage (%)   = Total Cost / Total Budget
i. Remaining (%)   = 100% - (Total Cost/Total Budget)%

Budget Revision
Budget revision proposal should be addressed to VP Finance & Performance along with the proper justifications.
Once the budget revision proposal is approved by VP Finance & Performance, it should be informed to Accounting for supplement & return process in SAP

Budget Commitment in SAP is on :
Purchase Requisition Final Approval
Purchase Order Final Approval (including VAT)
Budget Actualization in SAP is on :
Service : Service Entry Approval
Goods :  Goods Issue posting